Field Installation and Acceptance Procedure for KM8-A

Order Number: EK-KM8A-IN

This document outlines the installation and acceptance testing procedures for the Digital Equipment Corporation KM8-A memory extension and time-share option board.

Key details include:

  • Installation: Provides instructions for hardware inspection, physical installation into the Omnibus, and power-up testing.
  • Acceptance Procedure: Defines specific tests to ensure the KM8-A is functioning correctly within the system, including a table of programs to be run and their respective memory requirements.
  • Technical Schematics: The document provides detailed technical diagrams, parts lists, and switch configuration settings (Bootstrap/Auto-Restart, Auto-Restart Select, and various boot routines) for the KM8-A and Option Board #2 (M8317-YB).
  • Circuit Logic: Includes comprehensive wiring diagrams for the Memory Extension/Time-Share Register Control, Instruction Field, Data Field, IF & DF Save Field, and Instruction Buffer/User Buffer logic.